Heirloom, Kangaroo Point
Heirloom Purchaser update
Construction update · August 2026

Progress at Heirloom Kangaroo Point.

An update for purchasers on the construction of five full floor residences at 4 MacDonald Street, on the Brisbane riverfront.

Overview

Good morning.

We are pleased to report a productive month on site. The double height precast panels have been installed between levels 3 and 5, and the level 4 slab has been poured. The detail below sets out where each element of the build currently stands.

Construction status

Structural top-out on track for early October

Level 0 of 7 levels of structure
Design + approvals
Site establishment
Basement
Structure
Windows + facade
Fit-out
Handover
Precast to level 5

The double height precast panels have been installed between levels 3 and 5. The profile of the building is now visible from street level.

Level 4 slab

The level 4 slab, Residence 3, was poured on Wednesday 19 August.

Services installation

Services installation has commenced in the basement and on the ground floor, comprising the hydraulic, electrical and mechanical rough-in for the residences above.

Site photography

Recent progress on site.

Ben Teague, Managing Director of Molti, with Rob, Chief Executive of Graya, on site at Heirloom.

Project overview
Living room at Heirloom

Five full floor residences on the Brisbane riverfront.

Address4 MacDonald Street, Kangaroo Point
Residences5 full floor
Levels7 above ground, incl. rooftop
Basement1 level
ArchitectureBureau^Proberts
InteriorsCarr
The programme ahead
Window installation commencesEarly September
Lot 1 fit-out works commenceMid September
Passenger lift arrives on siteEnd of September
Structural top-outEarly October
On completion

The residences on completion.

From the Managing Director

Heirloom has begun to take its final form. We were on site on Wednesday to witness Apartment 3 slab being poured. Myself and Rob from Graya were lucky enough to see the project coming to life from the top of the crane.

We will continue to provide updates as the project progresses.

Ben TeagueManaging Director, Molti

Questions about your residence

Our team is available to assist with any question about your residence or the construction programme.

Contact the team